Ernest Johnson (EJ) Reserve in South Perth provides recreational, sporting and social opportunities for the local community.

In conjunction with Project Managers, NS Projects and architects Edwin Bollig Designs, the City of South Perth has engaged with stakeholders of Ernest Johnson Reserve to finalise the design for the Ernest Johnson Reserve Master Plan.

The Plan aims to accommodate the needs of relevant sports clubs, community groups, the local community and the City, and produce a contemporary, functional and sustainable multi-purpose facility.

The City was successful in securing $632,000 grant funding from the Department of Sport and Recreation for stage one of the project.

The final designs are now complete and have been submitted to the City for planning approval. The plans are available for comment until 5pm, Friday 29 January 2016.



Ernest Johnson (EJ) Reserve in South Perth provides recreational, sporting and social opportunities for the local community.

In conjunction with Project Managers, NS Projects and architects Edwin Bollig Designs, the City of South Perth has engaged with stakeholders of Ernest Johnson Reserve to finalise the design for the Ernest Johnson Reserve Master Plan.

The Plan aims to accommodate the needs of relevant sports clubs, community groups, the local community and the City, and produce a contemporary, functional and sustainable multi-purpose facility.

The City was successful in securing $632,000 grant funding from the Department of Sport and Recreation for stage one of the project.

The final designs are now complete and have been submitted to the City for planning approval. The plans are available for comment until 5pm, Friday 29 January 2016.



Consultation has concluded
  • EJ Reserve Redevelopment progress

    Share EJ Reserve Redevelopment progress on Facebook Share EJ Reserve Redevelopment progress on Twitter Share EJ Reserve Redevelopment progress on Linkedin Email EJ Reserve Redevelopment progress link

    Ernest Johnson (EJ) Reserve and its associated buildings are being redeveloped to better accommodate the needs of sports clubs, community groups, the local community and the City with the aim of providing a contemporary, functional and sustainable multi-purpose facility.

    Construction works for stage one of the $10.5m redevelopment are progressing well with structural steel installation taking shape on the main buildings.

    Ground slab works have been completed on the playgroup building and ground slab pours are in progress for the main hall and change rooms. Block work and underground pipe works are also under way on these buildings. The car park works have also commenced.

    This first stage of the project remains on schedule for completion at the end of 2017. The second stage, which will include demolition of existing buildings, works on the oval and construction of sports facilities, playgrounds and social areas, is scheduled to commence in early 2018.

    More information about this project can be found under the Projects and Places section of the City’s website.

  • Marking a milestone – soil turned at Ernest Johnson Reserve

    Share Marking a milestone – soil turned at Ernest Johnson Reserve on Facebook Share Marking a milestone – soil turned at Ernest Johnson Reserve on Twitter Share Marking a milestone – soil turned at Ernest Johnson Reserve on Linkedin Email Marking a milestone – soil turned at Ernest Johnson Reserve link

    The City of South Perth today marked a milestone when PACT Construction Pty Ltd., and architect Edwin Bollig together with the City’s Mayor Sue Doherty, Councillor Travis Burrows and CEO Geoff Glass, turned the first soil to mark commencement of works at Ernest Johnson (EJ) Reserve.

    Located in South Perth, bounded by South Terrace, Sandgate Street, and Hensman Street, EJ Reserve is one of the most well-known and popular playing fields in the City. The Reserve’s six associated buildings are being redeveloped to better accommodate the needs of relevant sports clubs, community groups, the local community and the City.

    A $10.5 million major project, the City’s EJ Reserve Master Plan will produce a contemporary, functional and sustainable multi-purpose facility and reserve.

    Works will be completed in two stages with the first stage including construction of new clubrooms, parking facilities and associated infrastructure. These works are due for completion at the end of 2017.

    The second stage will include civil works such as demolition of existing buildings, oval works, and construction of sports facilities, playgrounds and social areas. These works are due for completion in June 2018. Stage three of the Master Plan, which is not yet funded, includes the refurbishment of the Como Bowling Club and installation of paths and fitness stations.

    City of South Perth Mayor Sue Doherty said, “The turning of soil at the EJ Reserve is an enormous milestone in celebrating what promises to be a fantastic project, something our community has been highly involved with from the very beginning.

    “We look forward to the opportunities the facility will bring to all residents in the City, in particular those in the South Perth area.

    “The redevelopment of EJ Reserve provides the community with access to quality venues housing a range of groups including the South Perth Junior Football Club, South Perth Cricket Club, South Perth Playgroup, Girl Guides South Perth, Rotary Club of South Perth Burswood, Como Bowling and Recreation Club, South Perth Little Athletics, South Perth Junior Cricket Club.”